Fire Pump Start-Up Form

    As of July 2021, we will no longer be supporting Internet Explorer. While the majority of our site will function normally in this browser, we cannot guarantee that all aspects will function. Microsoft recommends upgrading to their Edge browser as they no longer support Explorer (including security updates). We would also recommend trying Google Chrome or Firefox. All three options are free downloads and well-supported.

    Project Name:*

    Is your pump new or a replacement?*

    Fire Pump Type:

    Requested Start-Up date**:

    Requested Start-Up time**:

    Requested Flow Test date with Fire Marshal**:

    Requested Flow Test time with Fire Marshal**:

    Requested date and time is not a guarantee. STH requires a minimum of 10 days notice.

    I need startup to occur as soon as possible. Please contact me if a date becomes available sooner than I have selected.

    Company Name:*

    Project Manager:*

    Project Manager Email:*

    Project Manager Phone Number:*

    On-Site Contact:*

    On-Site Email:*

    On-Site Phone Number:*

    Site Address:*

    City:*

    State:*

    Zip Code:*

    Please note any special parking instructions:

    Is a fire marshal required during the flow test?*

    Additional Notes:


    Will STH need to provide the outside flow equipment such as hose monsters and hoses? If so, how many of each?*

    NOTE: Contractor to provide skilled technicians to operate the outside portion of the test. In addition, the Contractor is responsible for set up and tear down of the outside equipment.

    How many hose monsters?*

    What length of hoses are needed from the test header?*

    Generator is load bank tested and ready (auto) so the transfer switch can be tested at start-up (if applicable)?*


    FREEZING TEMPERATURES

    NOTE: If required testing is to be performed in temperatures 35 degrees or lower, including wind-chill, there is a strong possibility the outside gauges will freeze & become unusable. If this occurs, you are responsible for the replacement cost of these gauges at $67.00 ea.

    STH requires 10 working days’ notice to schedule a start‐up. STH has allowed 3 hours on-site to perform start‐up on the pump system between 6:30am – 3:30pm, Monday – Friday. Any requests outside of these times / dates will be an additional charge. This form must be completed before anything can be scheduled.

    If the Start Up is canceled without 24 hours’ notice, you will be invoiced a $500 Cancellation Fee. Delays caused by other trades are your responsibility and do not absolve you of paying the delay and / or Cancellation Fee. Please make your Field Supervisor aware of these requirements and charges so they are ready when we arrive.

    Please note: that if STH arrives and the site items listed below are not ready for start-up and STH has to be rescheduled, then a return visit will require the contractor to provide an additional Purchase Order number for the original Full Start-Up amount to be charged as an extra. Any additional work during any start-up event beyond the standard scope will be invoiced at $147 per hour per man plus a $147 Travel Charge (Minimum $688) plus any materials needed.


    If the pump is powered by an ELECTRIC MOTOR the below items must be completed before STH arrives.

    • Due to safety concerns, it is a requirement for the contractor or their representative to remain on-site with the STH startup representative for the duration of the process.

    • Due to safety concerns, it is a requirement that a representative whom is English speaking be available to translate and provide communication assistance during the startup process.

    Electrical:

    • Electrical Inspection must be complete and a sticker/proper documentation must be onsite in the pump room.

    • A qualified electrician must be in the pump room during start-up/flow test to make any changes to the wiring.

    • Line & Load side power to the controllers/drivers must be completed per NFPA20 and NEC695.

    Hydraulic/Sprinkler Contractor Related:

    • A qualified sprinkler contractor must be onsite in the pump room the entire time STH is onsite.

    • Underground has been flushed to 150% of the fire pump rating. A hydraulic flush certificate must be provided. If the certificate is not provided or it does not meet the 150% criteria the sprinkler contractor and/or general contractor will be liable for any damage to the pump or delay due to the water supply.

    • The fire pump is mounted and secured with grout.

    • Water supply is on and system is ready to be charged/can have water flowing even with the discharge isolation
      open as required by the AHJ.

    • The fire pump and jockey pump sensing lines are connected at the proper points per NFPA.

    • All casing, pressure and air relief valves have been installed and are set at the proper set points.

    • If a main relief valve or pressure regulating valves are installed, all set points must be determined and adjusted
      by the sprinkler contractor.

    • All on and off set points for the fire and jockey pumps will be presented to STH or STH will set the points per
      NFPA.


    If the pump is powered by a DIESEL DRIVER the below items must be completed before STH arrives.

    • Due to safety concerns, it is a requirement for the contractor or their representative to remain on-site with the STH startup representative for the duration of the process.

    • Due to safety concerns, it is a requirement that a representative whom is English speaking be available to translate and provide communication assistance during the startup process.

    Diesel Electrical

    • A qualified electrician must be onsite in the pump room during the start-up and test to make an changes to the wiring.

    • Line and load side power to the fire and jockey pump controllers and drivers must be completed per NFPA20 and NEC695.

    • Engine jacket water heater is connected with AC electric.

    Diesel Hydraulic/Sprinkler Contractor Related:

    • A qualified sprinkler contractor must be onsite in the pump room the entire time STH is on site.

    • Underground has been flushed to 150% of the fire pump rating. A hydraulic flush certificate must be provided. If the certificate is not provided or it does not meet 150% criteria the sprinkler contractor and/or general contractor will be liable for any damage of the pump or delay due to the water supply.

    • The fire pump is mounted and secured with grout.

    • Water supply is on and system is ready to be charged/can have water flowing even with the discharge isolation open as required by the AHJ.

    • The fire pump and jockey pump sensing lines are connected at the proper points per NFPA.

    • All casing, pressure and air relief valves have been installed and are set at the proper set points.

    • If a main relief valve or pressure regulating valves are installed, all set points must be determined and adjusted by the sprinkler contractor.

    • All on and off set points for the fire and jockey pumps will be presented to STH or STH will set the points per NFPA.

    • Batteries to be filled with acid and charged 24 hours prior to STH arrival.

    • Confirm cooling water connections of the heat exchanger are proper and note damaged.

    • Confirm the exhaust connections are proper and most importantly supported without weight on the flex connector.

    • Fuel tank filled with diesel fuel.

    • Fuel inlet and return lines are connected properly.

    • Engine wiring between fire pump controller and engine wiring box is complete.

    It is clearly understood that the test header valves and manpower to control the valves and take readings are the responsibility of the Sprinkler Contractor.

    By completing this startup & flow test form I acknowledge that the fire pump/controller is completely ready to be started up and I have read & accept all of the above terms & conditions.

    Downloadable PDF Instructions:

    Wye‐Delta Open & Closed Transition and Part Winding
    ATL, Soft Start, Autotransformer, Primary Resistor and VFD